2018 – PCI Application
2019 – CEF Application
2020 – Grant Agreement, Start of implementation
- Start of construction of substation Öttevény (HU)
- Start of the tendering process for IT management system for smart grids (SCADA) (HU)
- Start of preparation of Action’s communication and dissemination plan
2021
- Start of construction of substation Gyermely (HU)
- Launch of the preparation of the tendering documentation for TS in Podunajske Biskupice substation (SK)
- Launch of the preparation of tendering procedure of optical fibre network – materials (SK)
- Signature of contract for IT management system for smart grids (SK)
- Communication Event 2021
2022
- Launch of the preparation of the tendering process for new substation near Šamorín (SK)
- Launch of the preparation of the tendering documentation for TS in Stupava substation (SK)
- Installation of optical fibre in HU and SK – 15 % completed
- Communication Event 2022
- 5% of the smart IT system implemented
2023
- 30% of TSs are commissioned (SK
- Launch of the preparation of the tendering documentation for the construction/reconstruction of the new/existing 110 kV substation in SK southern part
- Installation of optical fibre in HU and SK– 35 % completed
- 40% of the smart IT system implemented
- Communication Event 2023
2024
- Construction of five substations in HU completed
- Installation of TS in Podunajske Biskupice completed (SK)
- Installation of optical fibre in HU and SK – 60 % completed
- 65% of the smart IT system implemented
- Communication Event 2024
2025
- New substation near Šamorín commissioned (SK)
- Substation 400 kV Vajnory commissioned (SK)
- Communication system commissioned
- 100% of the smart IT system implemented
- Action close-up meeting