Danube InGrid

Smart grid Project of
Common Interest of the European Union

Action No. 10.7-0008-SKHU-W-M-20

The contents of this publication are the sole responsibility of Západoslovenská distribučná,
a.s., E.ON Észak-dunántúli Áramhálózati Zrt. and Slovenská elektrizačná prenosová
sústava, a.s. and do not necessarily reflect the opinion of the European Union.

About the project

  • Project Danube InGrid will adopt smart grid technologies both internally and on cross border level for the evolvement of modern energy infrastructure. It will efficiently integrate the behavior and actions of all market users connected to the electricity network, mainly consumers, prosumers and generators with the goal of integration of large amounts of electricity from renewable and/or distributed energy sources. Gaining and utilising experience in smart technologies in North Western Hungary and Western Slovakia, will be beneficial for electricity system users and distribution and transmission system operators.
  • The Danube InGrid project is on the current PCI list of the European Union
  • The Danube InGrid project is co-financed by the Connecting Europe Facility (CEF) of the European Union.
  • Project value: EUR 291 million
  • CEF co-financing: EUR 102 million
  • Implementation period: 2020 – 2025

Project
activities

  • Smart installations/devices on HV/MV (High Voltage/Medium Voltage) level
  • Transmission/distribution transformation
  • Optical fiber network on High Voltage and Medium Voltage network
  • IT management for smart grids
  • Action management, communication and dissemination

Project goal

News

Growing cities need smart grids

Západoslovenská distribučná, a. s. (ZSD) and Slovenská elektrizačná prenosová sústava, a. s. (SEPS) are introducing…

timeline

Events

28 June 2023

Public Consultation in Hungarian language in compliance with the Regulation (EU) No. 347/2013 of the European Parliament and of the Council of 17 April 2013 on guidelines for trans-European energy infrastructure – online eventinvitation and report.

27 June 2023

Public Consultation in Slovak language in compliance with the Regulation (EU) No. 347/2013 of the European Parliament and of the Council of 17 April 2013 on guidelines for trans-European energy infrastructure – online eventinvitation and report.

Public Consultation in Slovak language in compliance with the Regulation (EU) No. 347/2013 of the European Parliament and of the Council of 17 April 2013 on guidelines for trans-European energy infrastructure – online event, invitation and report.

Public Consultation in Hungarian language in compliance with the Regulation (EU) No. 347/2013 of the European Parliament and of the Council of 17 April 2013 on guidelines for trans-European energy infrastructure – online eventinvitation and report.

Public Consultation in compliance with the Regulation (EU) No. 347/2013 of the European Parliament and of the Council of 17 April 2013 on guidelines for trans-European energy infrastructure – online eventinvitation and report.

Public Consultation in compliance with the Regulation (EU) No. 347/2013 of the European Parliament and of the Council of 17 April 2013 on guidelines for trans-European energy infrastructure – online eventinvitation and report.

Public
consultation

You can send us your suggestions, observations
and queries via the form below and
we will be happy to answer them.

Implementation Plan

2018 – PCI Application

2019 – CEF Application

2020 – Grant Agreement, Start of implementation

Photos

2021

Photos

Photos

2023

  • 30% of TSs are commissioned (SK
  • Launch of the preparation of the tendering documentation for the construction/reconstruction of the new/existing 110 kV substation in SK southern part
  • Installation of optical fibre in HU and SK– 35 % completed
  • 40% of the smart IT system implemented
  • Communication Event 2023

Photos

2024

  • Construction of five substations in HU completed
  • Installation of TS in Podunajske Biskupice completed (SK)
  • Installation of optical fibre in HU and SK – 60 % completed
  • 65% of the smart IT system implemented
  • Communication Event 2024

Photos

2025

  • New substation near Šamorín commissioned (SK)
  • Substation 400 kV Vajnory commissioned (SK)
  • Communication system commissioned
  • 100% of the smart IT system implemented
  • Action close-up meeting